Summary
Cumberland County's proposed data-center standards would require electrical and water providers to attest to peak-load capacity while continuing service to other users. Staff say proposed SB 730 use requirements were incorporated into the draft even though the bill remains pending. Atlas is tracking a shift from pauses toward documented readiness conditions, alongside Charlotte's permit exemptions and Fayetteville's conditional rules. A pause is not a reset of existing entitlements. The next question is what evidence local standards would require before an application advances. Cumberland's Planning Board recommendation is unanimous; county adoption is not confirmed.